:: Question & Answer ::

Video Direct Link | Abstract

Abstract
ABS-244
Identification of Precast Box Girder Erection Activities to Develop Work Breakdown Structure in Elevated Railway Infrastructure Project
Nina Purwanti (a*), Pungky Dharma Saputra (a), Muhammad Hamzah Fansuri (a), Anasya Arsita Laksmi (a)
Corresponding Author: Nina Purwanti


Question from Mr. Verly Widiantoro
2020.11.18 14:05:35

From 13 activities in Box Girder Production, What is the main activities that have critical
time or take the longgest time and how to manage the activities in order not to interfere
with other activities.

Reply from Ms. Nina Purwanti
2020.11.18 14:44:09

Thanks for you question, Mr. Verly Widiantoro,

First of all, our research objective is actually to identify the 13 activities by
comparing statement method from three projects and then obtaining the expert
judgement and elected respondent. In the other hand, to answer your question, we
need a further research to discuss about cycle time of the method. However,
according
to our review the most critical activity is box girder delivery and hanging up
segment since it can cause delay to other activities behind it.

To manage the risks, we need to do identify the problem such as the traffic jam,
the problem in production and etc. On the other side, On site preparation needs to
be done properly.

Regards,