Identification of Precast Box Girder Erection Activities to Develop Work Breakdown Structure in Elevated Railway Infrastructure Project
Nina Purwanti (a*), Pungky Dharma Saputra (a), Muhammad Hamzah Fansuri (a), Anasya Arsita Laksmi (a)

(a) Military Building Construction Engineering, Faculty of Military Engineering, Indonesia Defense University, Bogor, Indonesia
*nina.setiadi1202[at]gmail.com


Abstract

The railway infrastructure development is being a concern to the government of Indonesia nowadays. One of construction methods mostly applied in building the railway infrastructure is box girder application with launching gantry. After observing several big projects with this method, some problems are identified. One of the problems is different work activities conducted during box girder erection. According to this situation, this research was conducted to identify precast box girder erection activities to develop work breakdown structure. The WBS will enhance the efficiency and effectivity of similar projects in the future. To conduct the analysis, there are three steps to be executed. They are archive analysis, expert judgement and surveys. For archive analysis, two big projects are observed and compared. Secondly, the judgements are obtained from five experts who have fulfilled more than ten years working experiences especially in public infrastructure construction. Thirdly, the direct surveys were held to thirty elected respondents regarding this topic. Finally, the descriptive analysis was applied to draw the result. This research conveys the WBS which has been developed according to aforementioned analysis method. There are 13 identified activities. They are preparation, box girder transportation, box girder lifting, position setting, epoxy gluing, temporary PT bar stressing, alignment surveying, PC stand and accessories installment, permanent stressing, patching, grouting and bearing installation re-surveying. This WBS is necessary to be used as a reference standard for future similar projects.

Keywords: activities- box girder- erection- work breakdown structure- railway- infrastructure

Topic: Engineering

Plain Format | Corresponding Author (Nina Purwanti)

Share Link

Share your abstract link to your social media or profile page

BISMAS 2020 - Conference Management System

Powered By Konfrenzi Ultimate 1.832L-Build7 © 2007-2025 All Rights Reserved