Base on this conclusion, that the average productivity of box girder is 38,95 hour.
In your opinion, with this production time duration, how many on going projects
can be handle by this box girder production speed capability in one production site?
Thans for your quetions,
About the number of project that can be handled in box girder production is depend the
capacity of line production at precast factory, the total number of box girder in project
and schedule of project. But from my research in Wika Beton Precast Factory, base on
their experience can handled until 3 until 5 project at same time production.